What it teaches
Rule 1 is the only one that does not add variation. Every other rule reacts to common-cause variation as if it were a signal; this is called tampering or over-adjustment. Rule 2 increases the standard deviation by about 41 % (the variance doubles), rule 3 makes the process oscillate with growing amplitude, and rule 4 turns it into a random walk that drifts away.
Where you see it on the shop floor
- An operator changes the machine offset after every measured part (rule 2).
- Each new batch is set up “to compensate” the last batch’s error (rule 3).
- A worker copies the last part instead of the master sample, or each training is given by the last trainee (rule 4).
The remedy is a control chart: adjust only when it shows a special cause. See it in the SPC simulator and test yourself in the SPC quiz.