Worked 8D case: oval, burred holes and punch breakage in stamping

An illustrative end-to-end case from a progressive die: customer complaint on Ø 8.5 mm pierced holes, containment, is / is not, Pareto, Ishikawa, 5 Why, MSA, Cpk before and after, Weibull punch life, PFMEA with AP, control plan, LPA and closure.

Ľubomír Blažek
Process quality team leader, automotive · updated 2026-11-11

Illustrative case. The company, the people, the part and all numbers are fictional and were created for teaching. The data are realistic in size and behaviour, and every statistic on this page is calculated from the published data with the same engines the tools use. Technical values such as die clearance are typical practice, not a specification: check them with your tool supplier and your customer requirements.

Scenario

A press shop stamps a steel seat-frame bracket in a progressive die on a 250 t mechanical press: strip 2.5 mm hot-rolled high-strength steel (S420MC), five stations, two pierced holes Ø 8.5 mm +0.10 / 0 (LSL 8.50, USL 8.60 mm), roundness 0.03 mm, burr height max. 0.15 mm. The holes take M8 fasteners at the customer’s assembly line.

In week 41 the customer rejects 37 brackets at assembly: the bolt does not enter, holes look oval and have a heavy burr. In the last four months the tool shop has replaced a broken Ø 8.5 punch five times, each time found only when parts with a missing hole were already in the box.

ItemValue
PartBracket, 2.5 mm S420MC, progressive die, two holes, ~1.2 million parts / year
CharacteristicPierced hole Ø 8.5 +0.10/0, roundness ≤ 0.03, burr ≤ 0.15 mm
Complaint37 parts rejected at customer assembly, week 41
Internal signal5 punch breakages in four months, no hit counter on the die
Result after 8DCpk 0.75 → 2.44 on diameter, punch changed every 80 000 hits, no breakage since

D1–D3 Team and containment

D1 Team. Emma Clarke (quality engineer, 8D leader), Lucas Martin (tool shop), Sofia Rossi (press shift leader), Mark Chen (maintenance), Anna Weber (supplier quality, for the coil supplier), Daniel Kim (metrology). Sponsor: plant manager.

D3 Containment, started within 24 hours:

  • Stock at the customer, in transit and in the plant blocked: 18 400 parts from 9 production lots.
  • 100 % sorting of every hole with a go / no-go pin gauge (go Ø 8.50, no-go Ø 8.60) and a visual burr check against a limit sample; an oval hole whose small axis is below 8.50 fails the go pin.
  • Clean parts marked with a green dot on the label; certified material to the customer from the next shipment, with the 8D number on the label.
  • Press: new punch, die clearance checked, first-off five parts measured with the bore gauge before restart.

Sorting result: 412 of 18 400 parts rejected (2.24 %), with 470 defects in total (one part can have several). Containment and the full 8D are documented in the 8D Report; the CAPA and NCR Tracker holds the actions with owners and dates.

Note the limit of the containment: a pin gauge checks the hole only at its smallest size. It does not measure roundness or burr height, which is why the sorting is backed by the visual burr check and why the permanent control (below) uses a bore gauge.

D2 Problem description: is / is not

Problem statement: Pierced Ø 8.5 mm holes in bracket station 3 are oval, undersize and burred, and the Ø 8.5 punches break in service (5 breakages in four months); defects found by the customer at assembly since week 39.

IsIs notWhat it tells us
WhatPierced hole Ø 8.5, station 3: oval, burr on one side, undersizeØ 12 hole (station 2), outer contour, bendsSpecific to the Ø 8.5 punch and its die button
WhereBoth holes, burr always on the side towards the strip edgeBurr all aroundOne-sided clearance: misalignment or guide wear
WhenIn the second half of a punch’s life (broken punches lasted 89 000 to 314 000 hits); more often on coils from one supplier batchRight after a punch changeWear-related, made worse by material variation
How much412 of 18 400 parts (2.24 %), 5 broken punches in four monthsEvery partIntermittent, grows with punch life

Pareto of the sorting result

The defects from the sort, as a Pareto chart. Three categories carry about 90 % of the defects, and all three point to the cutting condition of the punch and die rather than to handling.

DefectCountShareCumulative
Burr on hole edge21245.1 %45.1 %
Oval / deformed hole14831.5 %76.6 %
Hole undersize (go pin does not enter)6113.0 %89.6 %
Missing or partly pierced hole234.9 %94.5 %
Slug marks on surface173.6 %98.1 %
Other91.9 %100.0 %
Open this data in the Pareto chart →

MSA: can we trust the hole measurement?

Before trusting any capability number, the team checks the gauge: a digital two-point bore gauge, resolution 0.001 mm, which is 1 % of the 0.10 mm tolerance (rule of thumb: at most 5 %).

Type 1 study

50 repeated measurements on a setting ring Ø 8.550 mm by one operator. Mean 8.55078, bias 0.00078 mm, s = 0.00115 mm. With 20 % of the tolerance: Cg = 2.90, Cgk = 2.68, both above 1.33. The bias is statistically significant (50 readings detect even 0.8 µm) but small against the tolerance.

Open this data in the type 1 study →
Type 1 study data (50 values, mm)

8.550 8.550 8.551 8.551 8.551 8.549 8.549 8.553 8.551 8.551 8.551 8.551 8.550 8.551 8.552 8.550 8.551 8.551 8.551 8.552 8.552 8.549 8.550 8.552 8.551 8.550 8.550 8.551 8.550 8.552 8.550 8.550 8.553 8.550 8.550 8.549 8.551 8.550 8.550 8.551 8.552 8.550 8.548 8.552 8.552 8.553 8.552 8.553 8.550 8.550

Gage R&R (ANOVA), 10 parts × 3 operators × 3 trials

Ten parts covering the range seen in production, three operators (A, B, C), three blind trials each.

Source% of tolerance (6 σ)
Repeatability (EV)10.8 %
Reproducibility (AV)6.0 %
Total Gage R&R12.3 % (8.8 % of study variation)
Number of distinct categories15

%GRR of 12.3 % of tolerance is in the 10–30 % band that AIAG calls conditionally acceptable; against the process variation it is 8.8 % and ndc = 15, so the gauge separates parts well. The operator effect is statistically significant (p < 0.001) though small, the part × operator interaction is not (p = 0.70). The team accepts the gauge for this characteristic and adds a short instruction on how to centre the bore gauge in the hole. Roundness is measured on the CMM, which has its own MSA.

PartOperator AOperator BOperator C
18.51608.51908.5163
28.52738.52978.5250
38.53038.53008.5297
48.54278.54538.5437
58.54408.54338.5417
68.55508.55438.5533
78.56508.56678.5640
88.57308.57378.5717
98.57808.57838.5763
108.58738.58608.5840
Open this data in the Gage R&R →
Gage R&R raw data (90 readings, mm)
PartOperatorTrial 1Trial 2Trial 3
1A8.5178.5148.517
1B8.5208.5188.519
1C8.5178.5178.515
2A8.5288.5268.528
2B8.5298.5298.531
2C8.5278.5268.522
3A8.5298.5318.531
3B8.5298.5328.529
3C8.5298.5298.531
4A8.5438.5448.541
4B8.5458.5468.545
4C8.5428.5448.545
5A8.5448.5438.545
5B8.5458.5428.543
5C8.5428.5398.544
6A8.5548.5558.556
6B8.5548.5528.557
6C8.5548.5548.552
7A8.5658.5648.566
7B8.5668.5688.566
7C8.5678.5648.561
8A8.5748.5768.569
8B8.5748.5748.573
8C8.5718.5718.573
9A8.5768.5778.581
9B8.5778.5778.581
9C8.5748.5768.579
10A8.5868.5898.587
10B8.5898.5858.584
10C8.5828.5868.584

Capability before

25 subgroups of 5 consecutive parts, one subgroup per hour over three shifts, before any change. Nelson rules 1–3 switched on.

IndexHole Ø (LSL 8.50, USL 8.60)Roundness (USL 0.030)
Mean8.5197 mm0.0180 mm
Cp1.89n/a (one-sided)
Cpk0.75 (95 % CI 0.64–0.86)0.86
Ppk0.710.64
Out of spec in the sample2 of 1251 of 25
StabilityNot stable: downward run and trend (rules 2 and 3)Not stable: point beyond limit, run (rules 1 and 2)

The diameter story is in the gap between Cp 1.89 and Cpk 0.75: the spread would fit the tolerance almost twice, but the mean sits only 0.02 mm above the lower limit and drifts down as the punch wears (a punched hole takes the size of the punch). Expected out of tolerance from the overall sigma: about 16 906 ppm. Because the process is not stable, these indices describe what happened, not a prediction.

Open the diameter data (before) in the capability tool → Open the roundness data (before) →
Hole diameter before, 25 × 5 (mm)
#x1x2x3x4x5
18.5248.5408.5228.5328.534
28.5208.5338.5298.5298.537
38.5238.5188.5228.5408.519
48.5288.5188.5128.4988.522
58.5328.5208.5328.5368.535
68.5148.5258.5188.5338.534
78.5298.5378.5238.5268.509
88.5308.5208.5228.5158.521
98.5338.5188.5098.5228.513
108.5178.5248.4958.5188.531
118.5128.5198.5168.5198.521
128.5238.5148.5218.5288.537
138.5288.5288.5148.5168.508
148.5318.5298.5238.5088.517
158.5148.5168.5158.5138.524
168.5138.5098.5228.5278.510
178.5218.5218.5158.5108.513
188.5048.5158.5208.5128.523
198.5168.5208.5108.5048.512
208.5218.5318.5128.5108.507
218.5108.5088.5128.5348.506
228.5138.5138.5238.5388.509
238.5198.5228.5288.5008.525
248.5168.5068.5248.5148.513
258.5118.5218.5158.5128.513
Roundness before, 25 individual values (mm)

0.021 0.025 0.028 0.013 0.018 0.014 0.009 0.017 0.013 0.010 0.011 0.016 0.014 0.020 0.020 0.015 0.016 0.022 0.021 0.014 0.010 0.032 0.028 0.026 0.018

D4 Ishikawa (6M)

Brainstorming on the Fishbone Diagram with the press operator and the toolmaker at the press. Causes in bold were confirmed by checks or data; the others were checked and ruled out or found minor.

CategoryPossible causesCheck and result
MaterialSheet thickness and tensile strength variation between coils; punch material and hardness; coatingBroken punches measured 64–65 HRC against a drawing requirement of 60–62 HRC (too brittle). Coil certificates: Rm 505–610 MPa, within the S420MC range but the high-strength coils coincide with more breakages. Thickness within tolerance.
MachineDie clearance; punch-to-die alignment; stripper plate and guide bush wear; press shut height and speedGuide bushes of the stripper plate worn, 0.08 mm play; clearance uneven: 0.05 mm on one side, 0.20 mm on the other (2 % and 8 % of thickness). Shut height and speed as set.
MethodMaintenance interval; lubrication; punch change ruleNo hit-based punch change: punches run until they break. Lubricant applied, but the roller was dry on 2 of 6 checks.
MeasurementOnly go pin at first-off; no last-off checkNo no-go check and no roundness check in the control plan.
ManTraining of setters, reaction to a broken punchSetters trained; no instruction which parts to quarantine after a breakage.
EnvironmentSlug pulling, slug jamming in the dieSlug marks found (17 defects); die button has no slug retention feature, minor contributor.

D4 5 Why: occurrence and non-detection

Two chains in the 5 Why Analysis: why the defect was made, and why it was not caught.

Occurrence: why is the hole oval and the punch breaking?

  1. Why does the punch break? It is loaded sideways at every hit and fails in bending fatigue at the shank radius.
  2. Why is it loaded sideways? The clearance is uneven (0.05 / 0.20 mm), so the punch is pushed towards the wide side; the same deflection makes the hole oval and the burr one-sided.
  3. Why is the clearance uneven? The stripper plate guide bushes are worn (0.08 mm play) and no longer guide the punch.
  4. Why are they worn? The die is maintained only after a failure; there is no preventive interval based on the number of hits.
  5. Why is there no hit-based interval? The die has no stroke counter and the maintenance plan was set by calendar, not by use. Root cause (occurrence), together with the over-hardened punches from the punch supplier.

Non-detection: why did defective parts reach the customer?

  1. Why were the oval holes not detected? Only a go pin was used at the first-off check.
  2. Why only a go pin? The control plan specified it.
  3. Why did the control plan say so? It was copied from an older part with a ±0.2 mm hole and never reviewed in the PFMEA.
  4. Why were parts with missing holes shipped? After a punch breakage nobody knew since when the punch was broken: there is no last-off check and no rule to quarantine back to the last good check.
  5. Why no such rule? The reaction plan did not define it. Root cause (non-detection).

Weibull: punch life and change interval

The tool shop log has the hit counts at which the last 15 Ø 8.5 punches failed (about 18 months of records) (taken from the press counter at each change, all failures, no censored units):

89 000 · 129 000 · 172 000 · 178 000 · 184 000 · 191 000 · 208 000 · 209 000 · 212 000 · 215 000 · 218 000 · 218 000 · 227 000 · 278 000 · 314 000

Weibull fit by maximum likelihood: β = 4.31, η = 222 000 hits, B1 = 76 500, B10 = 132 000, mean life 202 000 hits. β well above 1 means wear-out: the failure rate rises with use, so a preventive change before failure is effective.

The team sets the change interval at 80 000 hits, close to B1. From this fit, the probability that a punch survives 80 000 hits is 98.8 %. A visual check of the punch and cutting edge is added at 40 000 hits. These lives were measured under the old, misaligned condition; the interval is conservative and will be reviewed after six months with the new punches (punches changed before failure then need a Weibull analysis with suspended data).

Open this data in the Weibull analysis →

D5–D6 Corrective actions

Root causeActionOwnerVerification
Worn guide bushes, uneven clearanceNew stripper guide bushes; guided punch with ball-lock retainer; die clearance reset to the value agreed with the tool supplier (typical practice for this steel and thickness: around 8–12 % of thickness per side, here 0.25 mm per side); clearance checked at every punch changeLucas MartinClearance record, hole roundness and burr on first-off
Over-hardened, brittle punchesPunch supplier: hardness requirement 60–62 HRC with certificate per batch; switch to powder-metallurgy HSS with a wear-resistant PVD coating as recommended by the tool supplierAnna WeberIncoming hardness check on 2 punches per batch
No hit-based maintenanceStroke counter on the die; punch change at 80 000 hits, punch inspection at 40 000; guide bushes checked every 500 000 hitsMark ChenCounter readings in the maintenance log
Dry lubrication rollerLubrication level and roller check at shift start, added to the press checklistSofia RossiLPA question 3
Detection: go pin only, no last-offControl plan updated (below): bore gauge first-off / last-off, X̄-R chart, in-die sensor, quarantine ruleEmma ClarkeCapability after, LPA

The clearance value is the tool supplier’s call: it depends on material strength, thickness, punch geometry and the hole quality you need. Tight clearance raises punch load and wear; large clearance gives more burr and rollover.

D6 Capability after

Same plan as before (25 subgroups of 5), over two weeks after all actions, including two punch changes at the counter limit.

IndexØ beforeØ afterRoundness beforeRoundness after
Mean (mm)8.51978.55060.01800.0096
Cp1.892.47––
Cpk0.752.44 (CI 2.13–2.75)0.862.22
Ppk0.712.210.642.62
StableNoYesNoYes

The diameter is now centred (mean 8.5506 against a mid-tolerance of 8.55) and stable; the Anderson-Darling test does not reject normality (p = 0.74). Roundness is a one-sided, zero-bounded characteristic; here the data pass the normality test (p = 0.28), otherwise a non-normal method would be needed. Both meet the usual requirement of Cpk ≥ 1.33 with a wide margin; the lower end of the 95 % interval for the diameter Cpk is 2.13.

Open the diameter data (after) in the capability tool → Open the roundness data (after) →
Hole diameter after, 25 × 5 (mm)
#x1x2x3x4x5
18.5538.5478.5538.5528.553
28.5448.5598.5468.5588.551
38.5378.5498.5428.5438.544
48.5598.5588.5538.5498.536
58.5428.5428.5508.5508.559
68.5488.5528.5598.5628.549
78.5498.5568.5518.5628.563
88.5588.5468.5568.5478.558
98.5488.5518.5368.5398.552
108.5458.5508.5558.5548.554
118.5668.5458.5588.5518.555
128.5538.5658.5498.5458.559
138.5488.5588.5568.5568.543
148.5478.5388.5418.5388.548
158.5418.5578.5478.5548.544
168.5488.5588.5638.5748.551
178.5568.5488.5528.5578.550
188.5588.5548.5558.5518.552
198.5518.5508.5478.5448.552
208.5388.5418.5548.5568.546
218.5428.5378.5518.5498.549
228.5518.5348.5388.5678.540
238.5628.5458.5478.5428.549
248.5548.5558.5428.5618.563
258.5488.5588.5548.5488.543
Roundness after, 25 individual values (mm)

0.007 0.012 0.009 0.011 0.009 0.005 0.007 0.014 0.005 0.011 0.006 0.011 0.013 0.009 0.009 0.009 0.007 0.012 0.007 0.010 0.012 0.009 0.013 0.013 0.010

D7 PFMEA update with AP

The PFMEA for station 3 had no line for punch breakage and rated detection of hole defects as if the hole were measured. Updated lines in the FMEA Worksheet with AIAG-VDA action priority:

Failure mode / causeBefore: S-O-D, APControl after actionAfter: S-O-D, AP
Hole oval / deformed
Punch deflects: worn stripper guide bushes, uneven die clearance
8-7-6, HighGuided punch, clearance check at every punch change, first-off / last-off bore gauge, X̄-R chart8-3-3, Low
Hole missing (punch broken)
Punch overload and brittle punch (64–65 HRC), no hit-based change
8-6-7, HighStroke counter with punch change at 80 000 hits, in-die slug / part sensor stops the press8-2-2, Low
Burr above 0.15 mm
Die clearance too large on one side, dull punch edge
6-6-6, MediumClearance set per tool supplier, punch inspection every 40 000 hits, burr check first-off / last-off6-2-4, Low

Severity stays the same (the effect on the customer has not changed); occurrence falls because of the guided punch and the hit-based change, detection improves through measurement and the in-die sensor. The ratings are illustrative: rate them with your own team and tables.

D7 Control plan update

Characteristic / process parameterMethodSample / frequencyReaction plan
Hole Ø 8.5 +0.10/0Bore gauge, X̄-R chartFirst-off and last-off 5 parts; 5 parts every 2 hOut of control or out of tolerance: stop, quarantine back to the last good check, 100 % check, inform shift leader
Roundness ≤ 0.03CMM1 part per punch change and per shiftOut of tolerance: stop, check punch, guide and clearance
Burr ≤ 0.15 mmVisual against limit sample, height gauge if in doubtFirst-off and last-off; every 2 hQuarantine back to last good check; inspect punch edge
Punch life (process parameter)Stroke counter on dieInspect at 40 000 hits, change at 80 000 hitsCounter limit reached: press stops until punch changed and first-off released
Punch breakage / missing holeIn-die slug / part sensor100 %, automaticPress stops; parts since last good check quarantined and checked 100 %
Die clearanceFeeler gauge / measured punch and die buttonAt each punch changeOut of agreed range: die to tool shop
LubricationVisual, level checkShift startRefill, check roller before restart

Build it in the Control Plan; the reaction plan is the part that most often fails in audits, so write who does what, not only “inform quality”.

D7 LPA questions

Questions added to the Layered Process Audit (LPA) for the press line:

  1. Is the punch hit counter below the change limit, and is the last change recorded with the clearance check?
  2. Are first-off and last-off hole checks for the current shift recorded, with the bore gauge, and inside the limits?
  3. Is the lubrication roller wet and the lubricant level above minimum?
  4. Is the in-die sensor active (test with the test piece at shift start recorded)?
  5. After the last stop for a broken punch or sensor alarm: were parts quarantined back to the last good check?

D7 Lessons learned

  • Tool wear is a process parameter: manage dies by hits, not by calendar or failure. Stroke counters were added to all progressive dies with pierced holes of class 1 tolerance.
  • A Cp much higher than the Cpk says “centre the process”; for a punched hole that means the punch size and its wear, not the press.
  • Never copy a control plan from another part without checking the tolerance; a go pin alone cannot check a two-sided tolerance.
  • Every detection method needs a defined reaction including how far back to quarantine.
  • Weibull on simple tool-shop records gave a defensible change interval in one afternoon; keep recording hits at every change.
  • Lessons transferred to the PFMEA family for pierced holes and to two other dies (read-across).

D8 Closure

Closure criteria agreed with the customer: three months without a complaint, no punch breakage, capability after ≥ 1.33 on diameter and roundness, and all actions verified in the CAPA and NCR Tracker. The team was recognised in the plant meeting and the 8D was closed in week 49 (illustrative). Certified-material marking was stopped after 30 clean shipments with the customer’s written agreement.

Try it yourself

Every data set above opens in the matching free tool. Change a number and watch the conclusion change: for example remove the drift from the “before” data and see how close Cpk gets to Cp.

Written by Ľubomír Blažek, process quality team leader, automotive. Illustrative case: fictional company, people and data.