QM BenchQuality engineering tools

Takt time and line balancing explained, with a Yamazumi example

How to calculate takt time, read a Yamazumi chart, find the bottleneck, calculate balance efficiency and the minimum number of stations, with a worked assembly cell case study.

Ľubomír Blažek
Process quality team leader, automotive · updated 2026-11-14

Try it while you read

Open the free Takt Time and Line Balancing (Yamazumi) tool and click Load sample: it reproduces the case study below.

Open the tool

Theory: takt, cycle time and balance

Takt time = available working time ÷ customer demand

Takt time is the pace of customer demand. A line meets demand when every station needs less than takt; the slowest station is the bottleneck and sets the line cycle time and the capacity. Because real stations lose time to small stops and variation, the work is planned against a planned cycle time somewhat below takt.

Balance efficiency = Σ station times ÷ (number of stations × slowest station)

Balance efficiency shows how evenly the work is spread. At 100 % every operator is equally loaded; at 70 % almost a third of the paid time is waiting. The minimum number of stations is the total work content divided by the planned cycle time, rounded up.

Key point

A Yamazumi chart stacks the work elements of each station as value adding, necessary non-value adding and waste. Remove the waste first: moving waste from one station to another does not improve anything.

Step by step

  1. Enter shift length, planned breaks, shifts per day and the customer demand per day.
  2. Set the planned cycle time as a percentage of takt, usually 85 to 95 % depending on the OEE of the line.
  3. Break each station into work elements, time each element over several cycles and classify it.
  4. Read the verdict, the Yamazumi chart and the station table: red stations are over takt, amber stations above the planned cycle.
  5. Use the rebalance proposal as a starting point and check it with the team for precedence, tools and ergonomics.
  6. Write the new sequence as a work instruction and audit it.

Case study: four-station assembly cell

The cell runs two shifts of 480 minutes with 40 minutes of breaks each, so 52,800 seconds are available. The customer takes 880 pieces a day: takt time is 60 seconds and the planned cycle at 90 % is 54 seconds (the Load sample).

  • Station loads: 41, 57, 37 and 16 seconds. Station 2 is the bottleneck: under takt, but 3 seconds above the planned cycle.
  • Work content 151 seconds, so 3 stations are enough at 54 seconds; balance efficiency of the 4-station line is 66 %.
  • Waste: 5 seconds walking at station 1, 6 seconds searching for screws at station 2.

The team puts screws in a point-of-use dispenser and moves the tool cart, removing 11 seconds. The torque check moves to the packing station. The result: 36, 42, 37 and 25 seconds, all below the planned cycle of 54 seconds. With 140 seconds of work content left, the next step is to test a three-station layout.

Common mistakes

  • Taking element times from the routing instead of measuring them.
  • Balancing to exactly 100 % of takt.
  • Ignoring the variation of manual times: a station that averages 54 seconds but often needs 65 will stop the line.
  • Calculating takt from capacity instead of demand.

Frequently asked questions

Should takt time include breakdowns?

No. Takt uses the available time after planned stops only. Unplanned losses are covered by planning the cycle time below takt, typically at 85 to 95 %.

What if demand changes every week?

Recalculate takt for each demand level and keep two or three prepared line configurations, for example with different numbers of operators, instead of rebalancing from scratch each time.