How to use the checklist
- Select the processes in scope. Each heat treat process you run has its own process table in the CQI-9 manual. Section 4 of this checklist asks whether you meet them.
- Rate every item with evidence. Satisfactory only when you can show a record, a procedure or the shop floor practice. Use N/A with a reason, for example no induction hardening.
- Add the action for each gap. Not satisfactory and needs immediate action open fields for the corrective action, owner and due date. The findings list on the right shows which actions are still missing.
- Do the job audit separately. Follow one real order from receipt to shipment through the records and compare it with the customer specification and the process table. Record what you find against the items here.
- Export the PDF with the report header (site, customer, CQI-9 edition, assessor) and keep it with the evidence for the customer and the IATF auditor.
The four sections
- Management responsibility and quality planning: heat treat specialist, quality planning, FMEA and control plan, specifications, change control, training, nonconforming product, records.
- Floor and material handling responsibility: receiving, identification and status, loading, lot integrity, suspect product after interruptions, reprocessing, traceability, packing.
- Equipment: thermocouples and instruments, system accuracy tests, temperature uniformity surveys, process monitoring and alarms, atmosphere and quench control, maintenance, laboratory equipment.
- Process tables: monitoring and test frequencies for each heat treat process, pyrometry intervals by furnace class, product tests and the reaction when a result is outside the limits.
Typical findings
- Temperature uniformity survey or system accuracy test overdue, or done on a smaller work zone than the one used in production.
- Process FMEA and control plan not updated after a change of quenchant, furnace or recipe.
- No rule for parts that fall from fixtures or baskets, or for parts in the furnace during a power loss.
- Hardness tester verified with a reference block that does not cover the hardness range tested.
- Customer specification revision not reviewed, so a stricter test frequency is missed.
Close repeated findings with an 8D report, and use the process capability tool for hardness and case depth data. For what CQI assessments are, who requires them and how they relate to IATF 16949, see the CQI special process hub.
The checklist items are our own short wording for preparing a self-assessment. They do not reproduce or replace the AIAG CQI-9 manual, which defines the official requirements and process tables. QM Bench is not affiliated with AIAG.
Frequently asked questions
What is CQI-9?
CQI-9 is the AIAG Heat Treat System Assessment. It checks whether a heat treating operation, in-house or commercial, controls its management system, material handling, equipment and pyrometry, and meets the monitoring and test frequencies in the process tables for each heat treat process.
Who has to do a CQI-9 assessment?
Every site that heat treats automotive parts for a customer that requires it in its customer-specific requirements, including commercial heat treaters working for automotive suppliers. The supplier that buys heat treatment must flow the requirement down and check that it is met.
How often is CQI-9 required?
Typically once a year as a self-assessment, and again after major changes such as new furnaces, a new location or a new process. The customer-specific requirements decide the exact interval and the edition to use.
What do S, NS and NIA mean?
Satisfactory means the requirement is met with evidence. Not satisfactory means a gap that needs a corrective action with owner and due date. Needs immediate action is a gap that can put product at risk now, such as an overdue temperature survey or a missing alarm, and needs containment before the fix.
What is the difference between SAT and TUS?
A system accuracy test (SAT) checks that the whole temperature measuring chain, sensor plus instrument, reads correctly against a reference. A temperature uniformity survey (TUS) checks that the temperature is the same, within tolerance, everywhere in the qualified work zone of the furnace.
Does this checklist replace the AIAG manual?
No. The items are short paraphrases written to help you prepare and track a self-assessment. The official assessment must follow the current AIAG CQI-9 manual and your customers’ requirements, including the job audit and the process table requirements in full.