Takt time
pace of customer demand
Takt = available working time ÷ customer demand
Takt time is the rate at which the customer takes products: the available working time in a period divided by the demand in the same period. Takt comes from the German word for the beat in music. It sets the pace every station of a line has to keep.
Available time is the shift time minus planned stops such as breaks and meetings. Breakdowns and other unplanned losses are not subtracted; they are absorbed by planning the cycle time somewhat below takt.
Example
Two shifts of 480 minutes with 40 minutes of breaks each give 880 minutes or 52,800 seconds. Demand is 880 pieces a day, so takt time is 60 seconds.
Common mistake
Calculating takt from what the line can produce instead of from what the customer orders.
Calculate it
Takt Time and Line Balancing (Yamazumi): Takt, bottleneck, balance efficiency and a Yamazumi chart per station.
Related terms
- Cycle time: time a station needs per piece
- Lead time: time from order or start to delivery
- Line balancing (Yamazumi): spreading work evenly across stations