Takt time

pace of customer demand

Takt = available working time ÷ customer demand

Takt time is the rate at which the customer takes products: the available working time in a period divided by the demand in the same period. Takt comes from the German word for the beat in music. It sets the pace every station of a line has to keep.

Available time is the shift time minus planned stops such as breaks and meetings. Breakdowns and other unplanned losses are not subtracted; they are absorbed by planning the cycle time somewhat below takt.

Example

Two shifts of 480 minutes with 40 minutes of breaks each give 880 minutes or 52,800 seconds. Demand is 880 pieces a day, so takt time is 60 seconds.

Common mistake

Calculating takt from what the line can produce instead of from what the customer orders.

Calculate it

Takt Time and Line Balancing (Yamazumi): Takt, bottleneck, balance efficiency and a Yamazumi chart per station.