Lead time
time from order or start to delivery
Lead time = WIP ÷ throughput (Little’s law)
Lead time is the time one piece or order needs to pass through the whole process, including all waiting. In most factories value-adding work is only a small fraction of the lead time; the rest is waiting in stock and queues.
Replenishment lead time, from a kanban card being released until the full container is back, decides the size of a kanban loop.
Example
2,000 pieces of work in progress and an output of 500 pieces a day give a lead time of 4 days, whatever the processing time is.
Calculate it
Kanban Calculator: Number of kanban cards, maximum stock and days of coverage per part.
Related terms
- Little’s law: WIP, throughput and lead time
- Value stream map (VSM): map of material and information flow
- Cycle time: time a station needs per piece