QM BenchQuality engineering tools

SMED explained: reduce changeover time step by step

The SMED method of Shigeo Shingo explained: internal and external work, four kinds of changeover work, conversion and streamlining, and a mould change case study from 132 to 39 minutes.

Ľubomír Blažek
Process quality team leader, automotive · updated 2026-11-14

Try it while you read

Open the free SMED Changeover Analysis tool and click Load sample: it reproduces the case study below.

Open the tool

Theory: internal, external and the four kinds of work

Changeover time = time from the last good part to the first good part at full speed

Only internal work, done with the machine stopped, counts as changeover time. External work happens while the machine is still producing. SMED first separates the two, then converts internal work to external, then streamlines both.

Shingo split changeover work into four kinds: preparation and cleanup, removing and mounting, setting and measuring, and trial runs and adjustment. In unimproved changeovers the last two often take half of the time, and they are the easiest to eliminate with fixed settings.

Key point

Separating internal and external work costs nothing and typically saves 30 to 50 %. Start there before buying quick-change hardware.

Step by step

  1. Film one changeover and list every step with its time.
  2. Mark each step internal or external as it is done today, and classify the kind of work.
  3. For each internal step decide: keep, convert to external, shorten or eliminate.
  4. Enter the changeovers per day to see the machine time freed.
  5. Test the new changeover, then write it as a standard with a checklist.

Case study: mould change on an injection moulding machine

The changeover took 132 minutes of internal time (the Load sample). The analysis shows that the next mould was fetched and preheated with the machine stopped, and that operators searched for clamps.

  • Converted to external: fetching (14 min) and preheating (25 min) the mould.
  • Eliminated: searching for clamps (8 min) with a prepared changeover cart.
  • Shortened: removing and mounting from 47 to 20 minutes with quick couplings and clamps, setting from 12 to 3 minutes with a stored parameter set, trial shots from 20 to 10 minutes.

The changeover falls to 39 minutes, −70 %. At three changeovers a day the machine gains 279 minutes. The plant uses the time for smaller batches and sizes the new kanban loops accordingly.

Common mistakes

  • Measuring from machine stop to machine start instead of last good to first good part.
  • Converting work to external without assigning who does it.
  • No standard after the workshop.

Frequently asked questions

How long does a SMED workshop take?

Usually two to five days for one machine: one day to film and analyse, one or two days to try the changes, and the rest to standardise and train. Hardware changes such as quick clamps may follow later.

Does SMED only work for presses and moulding machines?

No. It works for any changeover: CNC machines, packaging lines, filling lines, paint shops, cleaning between batches in food or pharma, and even operating theatres.