Kanban Calculator: Number of Kanban Cards and Supermarket Size

Calculate how many kanban cards each part needs with the Toyota formula, and see the maximum stock and the days of demand in every loop of your supermarket or two-bin system.How to use ↓Full guide with case study →
  • Free, no sign-up
  • Data stays in your browser
  • PDF report included

Part ofLean

Empty template

Fill in the form below, or load the sample to see a complete example and replace it with your own data.

  1. 1Enter or paste dataor click Load sample
  2. 2Read the verdictcharts and key figures
  3. 3Download the PDFwith your logo

Parts and replenishment

one row per part number; lead time = from card release to full container back at the line
PartDemand / day (pcs)Lead time (days)Review interval (days)Safety %Pcs per container
In-depth guide: theory, step by step and a worked case studyWritten by Ľubomír Blažek, process quality team leader, automotiveRead →

Kanban calculator: how many cards does a loop need?

Size kanban loops and supermarkets with the classic Toyota formula. For every part number enter the daily demand, the replenishment lead time, how often cards are collected, a safety factor and the pieces per container, and get the number of cards, the maximum stock in the loop and the days of demand it covers.

Several parts can be sized at once, so the calculator works for a whole supermarket, a two-bin system at a work station or production kanban between two processes. Notes flag loops with a single card, containers larger than the lead time demand and safety factors that hide a problem.

Worked example: Kanban Calculator

400 pcs a day, 1.5 days lead time, 0.5 day review, 10 % safety, 50 per box.
  1. 01Loop demand800 pcsD × (L + R)
  2. 02Safety+ 10 %880 pcs
  3. 03Cards17.6 → 18÷ 50 per container
  4. 04Stock900 pcs2.25 days of demand

01Method

Number of kanbans N = D × (L + R) × (1 + α) ÷ C, rounded up. D is the average demand per day, L the replenishment lead time, R the card collection or review interval, α the safety factor and C the container quantity. Lead and review time can be entered in days or in hours.

The maximum stock is N × C, the pieces in the loop when every card is full. Days of coverage = maximum stock ÷ daily demand. The average stock is roughly the safety stock plus half a container when demand is steady.

02When to use it

Use it to set up a supermarket at the line, to size two-bin systems for small parts, to agree production kanban between a feeding process and assembly, and to review loops when demand or lead time changes. Recalculate at least every time the customer schedule changes noticeably.

PDF report in one click

Export a PDF with the kanban table per part, the notes, the coverage chart and the formula used, ready for the supermarket board or the logistics team.

Private: runs in your browser

All calculations run in your browser. Part numbers and volumes are not uploaded.

How to size a kanban loop

  1. Take the average daily demand from the customer schedule, not from last month’s consumption peaks.
  2. Measure the replenishment lead time from card release to the full container back at the line.
  3. Set the collection interval: if cards are collected twice a shift, the interval is a quarter of a two-shift day.
  4. Choose the container: small enough to keep stock low, large enough to make handling worthwhile.
  5. Add a safety factor for the variation you see today, and lower it as the process becomes stable.
  6. Make the cards, start the loop and check daily for stock-outs and full supermarket lanes.

Worked example

A line uses 400 housings a day. The supplying process needs 1.5 days to replace a container, and cards are collected every half day. The safety factor is 10 % and a box holds 50 pieces. N = 400 × (1.5 + 0.5) × 1.1 ÷ 50 = 17.6, rounded up to 18 cards. A full loop holds 900 pieces, which is 2.25 days of demand. Halving the lead time to 0.75 days would bring the loop down to 12 cards and 1.5 days of stock.

Common mistakes

  • Using the processing time instead of the full replenishment lead time.
  • Rounding down to save a card, so the loop runs empty in the first busy week.
  • Never recalculating when demand or containers change.
  • Adding safety stock instead of fixing the cause of late replenishment.

Check that the line itself runs to takt with the takt time calculator, and cut the changeovers that force large batches with the SMED analysis. More lean tools are in the lean hub.

Frequently asked questions

›What is the kanban formula?

The classic Toyota formula is N = D × (L + R) × (1 + α) ÷ C. D is the daily demand, L the replenishment lead time in days, R the interval at which cards are collected, α the safety factor and C the number of pieces per container. The result is rounded up, because a fraction of a card does not exist.

›What belongs in the replenishment lead time?

Everything from the moment a card is released until the full container is back at the point of use: waiting for collection, transport to the supplying process, queue time, changeover, production or picking, and transport back. It is usually much longer than the pure processing time, so measure it instead of taking it from the ERP.

›How large should the safety factor be?

Large enough to cover the normal variation of demand and lead time, typically 10 to 20 %. A larger factor hides problems such as unreliable transport or long changeovers. Start with a moderate value, watch the loop and lower it as the process becomes stable.

›How many cards does a two-bin system need?

Two, one per bin. The bin size must cover the demand during the lead time plus safety, so the formula is used the other way round: container quantity ≥ D × (L + R) × (1 + α). The calculator shows the same result when you set the container quantity and get N = 2.

›Why do fewer cards mean improvement?

Each card is a container of stock. Taking cards out of a stable loop lowers the stock and makes the next problem visible, for example a long changeover or late transport. Solve that problem, then take out the next card. Shorter lead times and smaller containers reduce the number of cards for good.