SMED Changeover Analysis: Internal vs External Time, Before and After

List the steps of a changeover, mark what is done with the machine stopped, decide what to convert, shorten or eliminate, and see the changeover time before and after and the machine time it frees every day.How to use ↓Full guide with case study →
  • Free, no sign-up
  • Data stays in your browser
  • PDF report included

Part ofLean

Empty template

Fill in the form below, or load the sample to see a complete example and replace it with your own data.

  1. 1Enter or paste dataor click Load sample
  2. 2Read the verdictcharts and key figures
  3. 3Download the PDFwith your logo

Changeover steps

record the changeover from last good part to first good part, ideally on video
StepKind of workMinutesTodayActionNew minutes
In-depth guide: theory, step by step and a worked case studyWritten by Ľubomír Blažek, process quality team leader, automotiveRead →

SMED changeover analysis online

Analyse a changeover with the SMED method (single-minute exchange of die). List every step from the last good part of the old order to the first good part of the new one, mark whether it is done with the machine stopped (internal) or running (external), and decide for each step whether to keep it, convert it to external, shorten it or eliminate it.

You see the changeover time before and after, the reduction in percent, the remaining time by Shingo’s four kinds of changeover work and how much machine time the improvement frees each day. Use it for a SMED workshop, a kaizen event or to justify quick-clamping and preset tools.

Worked example: SMED Changeover Analysis

mould change on an injection moulding machine.
  1. 01Record132 mininternal steps today
  2. 02Separate− 39 minfetch mould, preheat while running
  3. 03Streamline− 54 minquick clamps, fixed settings
  4. 04Result39 min−70 %, next round

01Method

Changeover time is the internal time only: the minutes the machine does not produce. Steps converted to external move out of the changeover and must be done while the previous order is still running. Shortened steps count with their new time, eliminated steps drop out.

Machine time freed per day = (internal time before − after) × changeovers per day. Alternatively, the same total changeover time now allows before ÷ after times as many changeovers, so batches can be that much smaller.

02When to use it

Use SMED when changeovers limit capacity or force large batches, before you buy a new machine, as the agenda of a kaizen event, and to show management the effect of quick-change investments. It works for moulds, dies, fixtures, cleaning between products and product changes on packaging lines.

PDF report in one click

Export a PDF with the machine and the changeover, the verdict, the before and after figures, the chart by kind of work and the full step list with actions.

Private: runs in your browser

Your changeover data stays in your browser. Nothing is uploaded.

How to run a SMED analysis

  1. Film a real changeover from the last good part to the first good part at full speed.
  2. List every step with its time, and mark it internal (machine stopped) or external (machine running).
  3. Classify the work: preparation and cleanup, removing and mounting, setting and measuring, trial runs and adjustment.
  4. Convert internal steps to external: prepare tools, materials and the next die before the machine stops.
  5. Streamline what stays internal: quick clamps, fixed stops, stored settings, parallel work.
  6. Standardise the new changeover with a checklist and train everybody who does it.

Worked example

A mould change on an injection moulding machine takes 132 minutes of internal time. Fetching the next mould (14 min) and preheating it (25 min) move to external work. Searching for clamps (8 min) disappears with a prepared changeover cart. Quick couplings and clamps cut removing and mounting from 47 to 20 minutes, a stored parameter set cuts adjustment from 12 to 3 minutes and better first settings halve the trial shots to 10 minutes. The changeover falls to 39 minutes, −70 %. At three changeovers a day the machine gains 279 minutes, or the plant can change over about ten times a day in the time it uses for three today.

Common mistakes

  • Starting with expensive hardware before separating internal and external work, which costs nothing.
  • Forgetting trial runs and first-part approval in the changeover time.
  • Converting work to external without making sure someone does it before the machine stops.
  • No standard after the workshop, so the old habits come back within weeks.

See the effect on availability with the OEE calculator, use smaller batches with the kanban calculator and write the new changeover as a work instruction. All lean tools are in the lean hub.

Frequently asked questions

›What does SMED mean?

Single-minute exchange of die: a method developed by Shigeo Shingo to cut changeover times to below ten minutes, a single-digit number of minutes. The idea is to do as much of the changeover as possible while the machine is still running and to simplify what remains.

›What is the difference between internal and external work?

Internal work can only be done when the machine is stopped, for example removing the old die. External work can be done while the machine is still producing, for example fetching the next die, preheating it or preparing tools. Only internal work counts as changeover time.

›What are the steps of SMED?

First record the current changeover and separate internal from external work. Then convert internal work to external wherever possible, for example by preheating or presetting. Finally streamline both: quick clamps instead of bolts, fixed stops instead of adjustment, parallel work by two people, and standardised work.

›How is the changeover time measured?

From the last good part of the old order to the first good part of the new order at full speed. Trial runs, adjustment and first-part approval belong to the changeover; ignoring them makes the changeover look shorter than it is.

›What does a shorter changeover bring?

Either more productive time, which raises availability and OEE, or more changeovers in the same time, which allows smaller batches, less stock and faster response to customer orders. Lean plants usually use the second effect.