Little’s law
WIP, throughput and lead time
Lead time = WIP ÷ throughput
Little’s law states that in a stable system the average lead time equals the average work in progress divided by the average throughput. It holds regardless of the details of the process.
For lean it means: with the same output, the only way to shorten lead time is to reduce work in progress. That is why pull systems cap the stock between processes.