SMED (single-minute exchange of die)

quick changeover method

Changeover time = internal time only

SMED is Shigeo Shingo’s method for reducing changeover time to under ten minutes. The changeover is filmed and split into internal work, which needs the machine stopped, and external work, which can be done while it still runs.

Then internal work is converted to external wherever possible (prepare tools, preheat the die) and what remains is streamlined: quick clamps instead of bolts, fixed stops instead of adjustment, parallel work. Shorter changeovers allow smaller batches and raise availability.

Example

A mould change falls from 132 to 39 minutes by fetching and preheating the mould before the stop, quick couplings and stored settings.

Calculate it

SMED Changeover Analysis: Internal vs external steps, changeover time before and after, time freed per day.