QM Bench

VDA 6.3 Prozessaudit berechnen: Erfüllungsgrad EG und Einstufung A/B/C

Jede Frage mit 10 bis 0 Punkten bewerten und EPn, EG und die Einstufung A, B oder C erhalten. ↓

  1. 1Daten eingeben
  2. 2Bewertung lesen
  3. 3PDF-Bericht herunterladen

Hinweis: Die Bedienoberfläche des Werkzeugs ist derzeit auf Englisch; die deutsche Version folgt.

Saved in this browser

Score each question 10, 8, 6, 4 or 0. Starred (*) questions affect the downgrade rules; click the star to change it. Scores of 6 or less open fields for the finding and action.

P2 Project management

  • 2.1

    Project organisation with a project manager, team and responsibilities is established.

  • 2.2

    Resources for the project are planned and available, and changes are reported.

  • 2.3

    A project plan agreed with the customer exists and is tracked.

  • 2.4

    Advanced product quality planning is done and monitored for compliance.

  • 2.5

    Supply chain activities for the project (suppliers, purchased parts) are planned and monitored.

  • 2.6

    Change management in the project is controlled.

  • 2.7

    An escalation process is defined and used.

P3 Planning product and process development

  • 3.1

    Product and process requirements are specified, including customer-specific requirements.

  • 3.2

    Feasibility is assessed across functions for product and process requirements.

  • 3.3

    Activities for product and process development are planned in detail.

  • 3.4

    Customer care and support processes for the product are planned.

  • 3.5

    Required resources for product and process development are taken into account.

P4 Implementation of product and process development

  • 4.1

    Activities from the product and process development plan are carried out.

  • 4.2

    Human resources are available and qualified for series production.

  • 4.3

    Material resources (equipment, tools, gauges) are available and suitable.

  • 4.4

    Approvals for product and process development are in place.

  • 4.5

    Production and test specifications are derived from development and implemented.

  • 4.6

    A production trial run under series conditions is done for release.

  • 4.7

    Processes for handover to series production are in place.

P5 Supplier management

  • 5.1

    Only approved and quality-capable suppliers are used.

  • 5.2

    Customer requirements are passed on to the supply chain.

  • 5.3

    Target agreements for supplier performance are defined and implemented.

  • 5.4

    Purchased products and services have the necessary approvals.

  • 5.5

    Quality of purchased products and services is ensured.

  • 5.6

    Incoming goods are stored appropriately.

  • 5.7

    Personnel are qualified for their tasks in supplier management.

P6.1 Process input

  • 6.1.1

    The handover from development to series production is secured.

  • 6.1.2

    Required quantities and quality of input material are available at the agreed time.

  • 6.1.3

    Input material is stored suitably and identified.

  • 6.1.4

    Necessary approvals and documentation are available for the process.

P6.2 Process flow

  • 6.2.1

    Control plan exists, is complete and is applied.

  • 6.2.2

    Production is released (first-off) and released again after interruptions.

  • 6.2.3

    Special characteristics are controlled in production.

  • 6.2.4

    Nonconforming parts are segregated and handled correctly.

  • 6.2.5

    Material and part flow prevents mix-up and confusion.

P6.3 Personnel

  • 6.3.1

    Employees are responsible for monitoring product and process quality.

  • 6.3.2

    Employees are qualified for their tasks.

  • 6.3.3

    Staffing plans are in place, including substitution.

P6.4 Material resources

  • 6.4.1

    Production equipment and tools can meet the product requirements (capability).

  • 6.4.2

    Maintenance and tool management are controlled.

  • 6.4.3

    Measuring and test equipment can monitor the quality requirements effectively.

  • 6.4.4

    Workplaces and test areas are suitable for the requirements.

P6.5 Process effectiveness

  • 6.5.1

    Targets for the production process are set.

  • 6.5.2

    Quality and process data are collected and evaluable.

  • 6.5.3

    Deviations from product or process requirements are analysed and corrective actions are effective.

  • 6.5.4

    Processes and products are audited regularly.

P6.6 Process output

  • 6.6.1

    Output quantities match requirements and are passed on correctly.

  • 6.6.2

    Products and components are stored suitably and identified.

  • 6.6.3

    Correct packaging is used.

P7 Customer care and satisfaction

  • 7.1

    Quality management system requirements of the customer are met.

  • 7.2

    Customer support is ensured.

  • 7.3

    Supply of parts is ensured.

  • 7.4

    Complaints are analysed and corrective actions are implemented effectively.

  • 7.5

    Personnel are qualified for their tasks in customer care.

Photos (evidence)

VDA-6.3-Prozessaudit mit Einstufung A/B/C

Bewerten Sie ein Prozessaudit im Stil der VDA 6.3 online: 10, 8, 6, 4 oder 0 Punkte je Frage, Erfüllungsgrade EPn der Prozesselemente P2 bis P7, Gesamterfüllungsgrad EG und die Einstufung A, B oder C, mit automatisch angewandten Abstufungsregeln und Sternfragen.

Für Lieferantenaudits, Kundenaudits und interne Prozessaudits in Serie und Entwicklung.

So funktioniert es

Markieren Sie nicht bewertete Elemente als n.b., bewerten Sie jede Frage anhand von Nachweisen und erfassen Sie Feststellungen und Maßnahmen bei 6 Punkten oder weniger. Die Einstufung sinkt, wenn ein Element unter 80 % oder 70 % liegt, eine Sternfrage 4 Punkte oder eine Frage 0 Punkte hat.

Das Dashboard zeigt EG, Einstufung und die Elementergebnisse gegen die 80-%-Linie.

Wann einsetzen?

Nutzen Sie den Rechner für Lieferantenaudits vor der Vergabe und nach Qualitätsproblemen, zur Vorbereitung auf Kundenaudits und für interne Prozessaudits nach IATF 16949.

PDF-Bericht mit einem Klick

Exportieren Sie den Auditbericht als PDF mit Einstufung und Abstufungsgrund, Elementtabelle, Feststellungen und bewerteter Checkliste.

Vertraulich: alles läuft im Browser

Alles wird direkt in Ihrem Browser berechnet und gespeichert. Inhalte, Teilenummern und Fotos werden nicht hochgeladen. Keine Registrierung und keine Installation nötig; eine Sicherung aller Daten ist jederzeit als Datei möglich.

Häufige Fragen

Wie wird der Gesamterfüllungsgrad EG berechnet?

Als Mittelwert aller bewerteten Fragen in Prozent; nicht bewertete Fragen entfallen.

Warum wurde trotz EG über 90 % abgestuft?

Abstufungsregeln: Element unter 80 % oder Sternfrage mit 4 Punkten ergibt B; Element unter 70 % oder eine Frage mit 0 Punkten ergibt C.

Sind das die offiziellen VDA-Fragen?

Nein, eigene Formulierungen. Für offizielle Audits den lizenzierten VDA-Fragenkatalog verwenden und die Punkte eintragen.

Ausführliche Anleitung mit Fallbeispiel (Englisch)→