Takt time vs cycle time vs lead time: the difference
Takt time, cycle time and lead time compared: formulas, a worked example, what the comparison tells you and related terms such as processing time and planned cycle time.
Takt time, cycle time and lead time sound similar and are mixed up in many meetings. They answer three different questions: how fast must we be, how fast are we, and how long does a piece take from start to finish.
| Term | Question | Formula | Set by |
|---|---|---|---|
| Takt time | How often must a piece be finished? | Available time ÷ customer demand | The customer |
| Cycle time | How often is a piece actually finished? | Observed time between two pieces; the slowest station for a line | The process |
| Lead time | How long does one piece take through the whole process? | Work in progress ÷ throughput (Little’s law) | Process plus all waiting |
Worked example
A cell has 52,800 seconds a day and the customer takes 880 pieces: takt is 60 seconds. The slowest station needs 57 seconds, so the cycle time is 57 seconds and the cell keeps up. Between the cell and the moulding shop there are 2,640 housings in stock, and the cell uses 880 a day: the lead time of a housing through that buffer alone is 3 days, while its processing time is under a minute.
What the comparison tells you
- Cycle time above takt: the process cannot meet demand. Remove waste and rebalance, or add capacity.
- Cycle time far below takt: overcapacity. Either fewer operators or the risk of overproduction.
- Lead time much longer than the sum of cycle times: material waits. Reduce work in progress with pull and smaller batches.
Other times you will meet
- Processing time: the time a piece is actually worked on.
- Throughput time: often used as a synonym for lead time inside the plant.
- Planned cycle time: takt multiplied by a factor below 100 % to leave room for losses.
- Ideal cycle time: the fastest possible machine cycle, used for the performance factor of OEE.
Calculate takt and the station cycle times in the takt time calculator, check lost time at the bottleneck with the OEE calculator, and limit work in progress with the kanban calculator.