Value stream mapping tool online
Draw the current state of a value stream from your data: supplier, process boxes with cycle time, changeover time, uptime and operators, stock triangles with days of demand, finished goods and the customer.
The map checks every step against takt time, finds the bottleneck and the largest stock, and calculates lead time and the value-added ratio for the timeline at the bottom.
Worked example: Value Stream Map
- 01Takt60 s55,200 s ÷ 920
- 02Stock16,200 pcsin 6 places
- 03Lead time17.6 daysfor 188 s of work
- 04CheckAssembly 1 over takt62 s
01Method
Takt = available time per day ÷ demand per day. A step is over takt when cycle time ÷ uptime exceeds takt. Stock days = pieces ÷ daily demand. Lead time = Σ stock days + processing time; value-added ratio = processing time ÷ lead time.
PDF report in one click
Export a landscape PDF with the map, the verdict and the step table.
Private: runs in your browser
All data stays in your browser. Nothing is uploaded and no account is needed.
How to map the current state
- Choose one product family and enter its daily demand and the available time.
- Walk the flow from shipping back to receiving and enter each process with its data.
- Count the stock in front of each process and the finished goods.
- Read the map: red boxes are over takt; the timeline shows where the days of lead time sit.
Read the guide to value stream mapping, balance overloaded steps with the takt time calculator and replace stock with kanban loops. All tools: lean.
Frequently asked questions
›What data does a value stream map need?
For each process: cycle time, changeover time, uptime, number of operators and, between the processes, the stock counted on the floor. From the customer: demand per day and the available working time, which give the takt time.
›Why divide the cycle time by the uptime?
A machine that is down 20 % of the time needs a faster cycle to keep up. Cycle time ÷ uptime is the effective time per part and is compared with takt.
›What is a good value-added ratio?
In most factories it is far below 1 %: minutes of processing in days or weeks of lead time. The absolute value matters less than the trend after improvements.
›Does the tool draw a future state?
Draw the future state as a second map with the planned stock levels, supermarkets and cycle times, and compare the lead times. The guide to value stream mapping lists the future-state questions.