EPEI calculator for heijunka
Enter the products of a shared machine with daily demand, cycle time and changeover time, and the available time per day. The tool calculates how often each product can be made (every part every interval), the lot sizes and the machine load.
Use it to see how far changeover reduction lets you level the product mix, and to size the supermarket after the machine.
Worked example: EPEI and Heijunka Calculator
- 01Run time536 mindemand × cycle
- 02Free364 minfor changeovers
- 03EPEI0.41 days150 min ÷ 364
- 04LotsA 248, B 124 …demand × EPEI
01Method
EPEI (days) = Σ changeover times ÷ (available time − Σ demand × cycle time). Lot size = daily demand × EPEI, rounded up.
PDF report in one click
Export a PDF with the product table, EPEI, lot sizes and the chart.
Private: runs in your browser
All data stays in your browser. Nothing is uploaded and no account is needed.
How to use it
- Enter the available time of the machine per day after breaks and planned stops.
- List every product with its daily demand, cycle time and changeover time.
- Read EPEI and the lot sizes; a negative free time means the machine is overloaded.
- Test changeover reduction by lowering the changeover times and see EPEI fall.
Cut changeovers with the SMED analysis and size the supermarket after the machine with the kanban calculator. Background: heijunka.
Frequently asked questions
›What is EPEI?
Every part every interval: the time it takes to produce every product of a machine once, including changeovers. An EPEI of 0.5 days means each product can run twice a day; 5 days means once a week.
›How is EPEI calculated?
The time left for changeovers per day is the available time minus the run time for the daily demand of all products. EPEI in days is the total changeover time for one cycle through all products divided by that free time.
›What is heijunka?
Levelling the production of different products over the day or week instead of running big batches. A short EPEI is the precondition for heijunka; a heijunka box then distributes the kanban cards in time slots.
›How do I shorten EPEI?
Shorter changeovers lower EPEI directly: halving the changeover time halves the lot sizes and the stock in the supermarket after the machine.