Standardized work combination sheet online
Enter the work elements of one operator with manual time, machine running time and walking time, and get the combination chart against takt time, as used in standardized work.
The tool finds the cycle time, shows when a machine rather than the operator sets the pace, how long the operator waits, and how much of the cycle is walking.
Worked example: Standardized Work Combination Sheet
- 01Manual43 s5 elements
- 02Walking15 sbetween machines
- 03Machinelathe 38 sruns in parallel
- 04Cycle58 sclose to takt
01Method
Manual and walking time follow each other on the operator’s time line; machine time starts at the end of the manual step. Cycle time = max(operator time, manual + machine time of any element).
PDF report in one click
Export a landscape PDF with the chart and the element table.
Private: runs in your browser
All data stays in your browser. Nothing is uploaded and no account is needed.
How to fill in the sheet
- Enter takt time from the customer demand.
- List the work elements of one operator in the order they are done.
- Enter manual, machine and walking time for each element.
- Read the chart: the red line is takt; the green dashed line is the resulting cycle time.
- Reduce walking and waiting before you add operators or machines.
Calculate takt with the takt time calculator, measure walking with the spaghetti diagram and document the sequence in a work instruction. See also standardised work.
Frequently asked questions
›What is a standardized work combination sheet?
A chart of one operator’s work cycle that combines manual work, machine running time and walking on one time axis against takt time. It shows whether the operator can run the sequence within takt and where time is lost.
›Why can a machine set the cycle time?
The operator returns to each machine once per cycle. If the manual load time plus the machine running time of one machine is longer than the operator’s walk around the cell, the operator waits at that machine.
›Where do the times come from?
From a time study at the station: several observed cycles per element, the lowest repeatable time for manual work, and the machine cycle from the machine itself.
›How is this different from a work instruction?
The combination sheet shows timing and sequence; the work instruction describes how each step is done with key points and reasons. Both are part of standardized work.